PRELIMINARY
DCN/ICN PILOT PROGRAM TEST PLAN
for the
DOD CALS IDE PROJECT
January 1997
Submitted to
D.N. AMERICAN, INC.
1000 Technology Drive, Suite 3220
Fairmont, WV 26554
In support of
Contract No. DEAM21-96-MC32239
T.O. No. HQ00038-6199-0002
CDRL Sequence Numbers A010

______________________ |
______________________ |
TABLE OF CONTENTS
LIST OF FIGURES
LIST OF TABLES
1.0 INTRODUCTION
1.1 Identification
1.2 System Overview
1.3 Document Overview
1.4 Applicable Documents
2.0 DCN/ICN PILOT PROGRAM TESTING ENVIRONMENT
2.1 Introduction
2.2 Risk Analysis
2.3 Test Levels and Strategy
2.4 Test Methods
2.5 Participating Organizations
2.6 Facilities
2.7 Personnel
2.8 Equipment
2.9 Test Schedule and Resources
3.0 DCN/ICN TEST AREAS (SERVICES)
3.1 Subscriber Services
3.2 Information Content Provider Services
3.3 Advertiser Services
3.4 Test and Implementation Activities By Service Area
3.4.1 SVC100 General Services
3.4.2 SVC1800 Advertising Services
3.4.3 VC700 Training
3.4.4 SVC400 Calendar of Events
3.4.5 SVC500 Electronic Mail Services
3.4.6 SVC1900 Electronic (Web) Publishing
3.4.7 SVC2000 Internet Hardware/Software Acquisition and Installation
3.4.8 SVC200 Organizations
3.4.9 SVC800 Information Services
3.4.10 SVC900 Collection of Comments
3.4.11 SVC1300 Specialists
3.4.12 SVC300 CALS Initiatives
3.4.13 SVC1000 Standards
3.4.14 SVC1600 Computer Supported Collaboration
3.4.15 SVC600 Technologies
3.4.16 SVC1100 Publications
3.4.17 SVC1200 Implementations
3.4.18 SVC1400 Partnership Search
3.4.19 SVC1700 Dissemination Service
3.4.20 SVC1500 Test and Certification
3.5 Test Data Recording, Reduction, and Analysis
3.6 Requirements Traceability
3.7 Notes
APPENDIX A: WORKSTATION AND SERVER QUALIFICATION CRITERIA FOR DCN/ICN COLLABORATION AND INFORMATION SERVICES
APPENDIX B: CALS ICN/DCN SITE CONFIGURATION SURVEY
APPENDIX C: SECURITY ARCHITECTURE
APPENDIX D: ABBREVIATIONS AND ACRONYMS
Figure 1.2-1 DCN/ICN Organizations and Relationships
Figure 1.2-2 DCN/ICN MOCC Configuration
Figure 2.2-1 Software Requirements Process Model
Figure 2.2-2 Software Test Phase Process Model
Figure 2.3-1 DCN/ICN Types and Levels of Service
Figure 2.3-2 Test Strategies for COTS and Developmental Items
Figure 2.6.2-1 Preliminary Facility Layout for the MOCC
Figure 3.4-1 DCN/ICN Preliminary Activity Schedule for Prototype Testing and Implementation