Table Of ContentsNext Page

PRELIMINARY
DCN/ICN PILOT PROGRAM TEST PLAN

for the

DOD CALS IDE PROJECT

January 1997

Submitted to
D.N. AMERICAN, INC.
1000 Technology Drive, Suite 3220
Fairmont, WV 26554

In support of
Contract No. DEAM21-96-MC32239
T.O. No. HQ00038-6199-0002

CDRL Sequence Numbers A010

 

 

______________________

______________________

Robert S. Kidwell
Jack G. Richman
Senior Technical Director
Executive Director
DoD CALS IDE Project
DoD CALS IDE Project

 

TABLE OF CONTENTS


LIST OF FIGURES
LIST OF TABLES
1.0  INTRODUCTION

2.0  DCN/ICN PILOT PROGRAM TESTING ENVIRONMENT

3.0  DCN/ICN TEST AREAS (SERVICES)

APPENDIX A:  WORKSTATION AND SERVER QUALIFICATION CRITERIA FOR DCN/ICN COLLABORATION AND INFORMATION SERVICES
APPENDIX B:  CALS ICN/DCN SITE CONFIGURATION SURVEY
APPENDIX C:  SECURITY ARCHITECTURE
APPENDIX D:  ABBREVIATIONS AND ACRONYMS

 

LIST OF FIGURES


Figure 1.2-1  DCN/ICN Organizations and Relationships
Figure 1.2-2  DCN/ICN MOCC Configuration
Figure 2.2-1  Software Requirements Process Model
Figure 2.2-2  Software Test Phase Process Model
Figure 2.3-1  DCN/ICN Types and Levels of Service
Figure 2.3-2  Test Strategies for COTS and Developmental Items
Figure 2.6.2-1  Preliminary Facility Layout for the MOCC
Figure 3.4-1  DCN/ICN Preliminary Activity Schedule for Prototype Testing and Implementation

 