APPENDIX H: LIST OF POSSIBLE CALS IMPROVEMENT TARGETS


LIST OF POSSIBLE CALS IMPROVEMENT TARGETS
Real life examples still need to be selected from available resources and added in the following tables. Improvement targets starting at "Automate Change Management" need to be detailed.

Table H-1 Requirement Management

Improvement Target

Requirement Management
(Pre and Post Contract Award)

Description

Software tool used to manage the requirement document in a structured form through life. Enables better control of the requirements and easier management and traceability of changes.

         

Application/ Benefits

 

Time

Quality

Cost

Pre-
production

 

We know what we are meant to do and who asked for it.

· Do the right thing.
· Provides good baseline for justification of changes.

Production

 

Use

· Better baseline for in service CM.
· Maintaining a valid and current structured requirement statement during the in-service phase, it provides a better baseline for decisions on support planning and upgrades.

Example

 

 

Table H-2 Shared E-Mail and Office Software

Improvement Target

Shared E mail and Office Software
(between program participants)

Description

 

Application/ Benefits

 

Time

Quality

Cost

Pre-
production

Faster communications lead to faster decisions.

 

· Quicker is cheaper.
· Some potential for travel savings.

Production

 

Use

 

Example

 

 

Table H-3 Electronic Program Document Library

Improvement Target

Electronic Program Document Library

Description

Central managed source of significant documents (e.g., requirement, contract, Specs, policy, etc.) (Scope - office docs, drawings, models, video, etc.)

Application/ Benefits

 

Time

Quality

Cost

Pre-
production

Time reduction in retrieval and distribution.

Much improved change control and CM.

Reliable data gives better decisions. (Technology is cheap but set up and operating costs are non trivial)

Production

Use

Example

 

 

Table H-4 Improve Program Management

Improvement Target

Improve Program Management

Description

Use of Common Program Management tool set for project planning and control (Tasks, Resources WBS, CSCS, Plans)

Application/ Benefits

 

Time

Quality

Cost

Pre-
production

· People know what to do when.
· Better visibility of project status.

Some improvement.

Better resource management.

Production

Use

     

Example

 

 

Table H-5 Program Workflow System

Improvement Target

Program Workflow System

Description

Allows standardization, simplification, and automation of work in processes.

Application/ Benefits

 

Time

Quality

Cost

Pre-
production

Major savings possible

Enforces adherence to defined process

Can deliver substantial savings on repetitive processes.

Production

Use

Acts as a major stimulus and support for Business Process Improvement. Big cultural issues.

Example

JCALS
Those who use the environment have found it easy to make changes to electronic workflow to achieve process improvements. The workflow manager allowed them to see the opportunities for improvement and make changes to the automated workflow rather than having to notify others to carry out new routing procedures.

(Source: DoD IDEHDBK)

 

Table H-6 Implement a Virtual Design Environment

Improvement Target

Implement a Virtual Design Environment

Description

A Shared Data Environment for design, facilitating working concurrently on the same design (data)

Application/ Benefits

 

Time

Quality

Cost

Pre-
production

· Saves traveling time.
· Concurrent working speeds up design time.

 

Saves on traveling expenses.

Production

     

Use

     

Example

Computer modeling was used almost exclusively to design and build the first test aircraft (no mock-ups), resulting in:
· Product to market time substantially reduced
· Quality improvement remarkable with alignment of first aircraft in hundredths of inches
· Added aircraft performance (e.g., lower fuel consumption) due to team input, higher quality and resultant superior products

(Source: IDEBAT, slide 24)

 

Table H-7 Implement a Virtual Design and Test Environment

Improvement Target

Implement a Virtual Design and Test Environment

Description

A Shared Data Environment for design and testing of the design, facilitating working concurrently on the same design (data) and test the design without building prototypes, e.g., virtual mock-up.

Application/ Benefits

 

Time

Quality

Cost

Pre-
production

· Saves traveling time.
· Concurrent working speeds up design time, not having to build physical prototypes for testing.
· Concurrent testing and redesign possible

· Allows for testing a great deal of design-variants.
· Allows for testing under many simulated (hazardous) environments and conditions.

· Saves on traveling expenses.
· Saves because not having to build prototypes.

Production

     

Use

     

Example

 

 

Table H-8 Improve Configuration Management (CM)

Improvement Target

Improve Configuration Management (CM)

Description

Single logical CM system for project, used as index for most product information.

Application/ Benefits

 

Time

Quality

Cost

Pre-
production

Some benefits due to better access to information.

· Control of requirement and requirement changes.
· Control of emergent design.

Some benefits due to better access to information.

Production

Less time needed to find information.

Consistent CM info through the supply chain.

 

Use

Savings in maintenance time through better information.

We know what we have to support.

· Minimize rework.
· Minimize unnecessary purchases

Example

 

 

Previous PageTop Of PageNext Page