updated on 12/09/2001 Task Leader: Lt. Col. Robert Herreman

Task 2.1 description:

Define and document, using a process analysis methodology, the NATO LCI business environment (NATO Defence System Through Life Business Model) and the information requirements to support each process identified.

Task Planning:                                                  

  Task Name Duration Start Finish

Resource

2.1
Define and document , using a process analysis methodology, the NATO LCI business  environment and the information requirements to support each process identified.

T.B.D.

2/01/01

T.B.D.

 
2.1.1
    Document ISO 15288 Business Model
176 days

2/01/01

25/06/01

R.H +C.B. (75)

2.1.2

Taylor 15288 business Model to NATO LCI environment (NATO DS TLBM)

66 days

26/06/01

31/08/01

R.H. (33)

2.1.3
Identify information requirements
332 days

2/01/01

30/11/01

R.H. (87)

2.1.4
Perform NPDMl/Info-Req Gap analysis and investigate further work

T.B.D.

30/11/01

T.B.D.

R.H. + B.T. (98)

Deliverables:

Resources required:

293 NCO man days

Success Measures:

Publish the NATO DS through life Business Model and document LCI  information requirements by November 2001.

Status Report:

An IDEF0 modelling describing the Defence System TLBM, based on Draft ISO-15288, has been completed and will be shortly distributed for comments.