updated on 12/09/2001 Task Leader: Maj. Senol Sevim

Task 3.2 description:

Extend the use of existing NATO LCI concepts/products/services by active business change agents in NATO, Multinational and National projects to accelerate the implementation of LCI.

Task Planning:                                               

  Task Name Duration Start Finish Resource Names
3.2

Extend the use of NATO LCI concepts/products/services 

continuous

 

 

 
3.2.1

    Identify projects willing to co-operate

As occur

 

 

S.S.

3.2.2

Seek Committee approval on co-operations

As occur

 

 

S.S.

3.2.3

Provide awareness/services to project

As planned

 

 

 

.1

        Provide services to Viking

As planned

 

 

B.T. (15)

.2

        Provide services to NETMA

As planned

 

 

B.T. (15), G.G.(15)

.3

        Provide services to AGS

TBD

 

 

TBD

.4

       Provide services to TU CALS

As planned

 

 

TBD

Deliverables:

Not applicable.

Resources required:

TBD

Success Measures:

Increase NATO/National programmes adoption of NATO LCI concepts/products between 2000 and 2002.

Status Report:

A one-week workshop in the NCO is planned for mid October. This will be a continuation of the support provided to the Turkish initiative, and will in detail discuss NPDM and Implementation issues.