updated on 12/09/2001 Task Leader: Lt.Col. Dieter K. KLEMM

Task 4.2 description:

Maintain awareness of technological developments and potential application through close liaison with industry.

Task Planning:                                        

  Task Name Duration Start Finish Resource Names
4.2 Maintain awareness of technological developments and potential application through close liaison with industry.

continuous

 

 

 
4.2.1  Establish / renew and maintain relationship with NICG, NICG-E or successor organizations

continuous

 

 

D.K. (5)

4.2.2

Develop procedures for industry support and cooperation with CPG on LCI

304 days

02.01.2001

01.10.2001

D.K. (10)

4.2.3 Monitor activities of multinational industry groups on LCI related issues and information management

continuous

 

 

D.K. (10)

4.2.4 Inform and (if appropriate) provide tutorials to NCO members and presentations to CPG

As occur

   

D.K. (5)

4.2.5 Actively participate in the Joint Industry - government Working Group on Integrated Technical Data Issues (former NATO -IETM WG) to improve interoperability of technical documentation over the life cycle

T.B.D. 

 continue

T.B.D. 

D.K. (10)

Deliverables:

Not applicable.

Resources required:

40 NCO man days.

Success Measures:

Not applicable.

Status Report:

  • NATO ITD INTEROPERABILITY TASK FORCE (Ex NCMB IETM Working Group). (DK)

The meeting 07-09 August 2001 focussed on an ITD Interoperability Roadmap and a raw structure was agreed. Details of the meeting was distributed to the POC by separate e-mail (NCMB(NCO)-(01) 49) for information.