updated on 23/02/2001 Task Leader: Mr. Graeme Glenister

Task 6.2 description:

Establish NATO Policy on the use of metrics within programs and projects.

Task Planning:                                               

 Task NameDurationStartFinish

Resource 

6.2
Establish NATO Policy on the use of metrics within programs and projects 

365 days

01/07/2001

30/06/2002

 
6.2.1
   Identify interested NATO bodies and form Working Group

121 days

01/07/2001

30/10/2001

G.G. (30)

6.2.2

Produce Metrics Policy Draft

121 days

01/11/2001

28/02/2002

G.G. (62)

6.2.3
Issue Metrics Policy Draft for comments

60 days

01/03/2002

30/04/2002

G.G. (30)

6.2.4
     Finalizes Metrics Policy Draft

31 days

01/05/2002

31/05/2002

G.G. (15)

6.2.5
        Secure CPG endorsement

 

Jun/2002

Jun/2002

G.G.  (1)

6.2.6
Circulate to NADreps

90 days

30/06/2002

30/09/2002

G.G. (11)

6.2.7
      Secure CNAD endorsement

 

Oct/2002

Oct/2002

G.G. (1)

Deliverables:

NATO Policy on the use of metrics within programs and projects.

Resources required:

150 NCO man days.

Success Measures:

Publish NATO Policy on the use of metrics within programs and projects by October 2002.

Status Report:

New Task.