updated on 12/09/2001 Task Leader: Mr. Mike Danielsen

Task 7.1 description:

Manage the transition of activities, products and skills, from the NCO and NCMB to the new CPG.

Task Planning:                                        

Task # Task Name Duration Start Finish

Resource

7.1

Manage the transition of activities, products and skills, from the NCO and NCMB to the new CPG.

730 days

02/01/01

31/12/02

 
7.1.1

Define and document NCMB/NCO activities and products of interest to the new CPG and assess skills and efforts required to support and maintain them.

182 days

02/01/01

30/06/01

M.D. (5)              B.T. (15)                 R.H. (10)                G.G. (5)                  D.K. (5)

7.1.2

Establish methods and procedure for transfer of responsibility of NATO CALS activities and products.

182 days

30/06/01

31/12/01

M.D. (10)              B.T. (20)                 R.H. (15)                G.G. (5)                  D.K. (5)

7.1.3

Perform transfer of responsibility of NATO CALS activities and products.

365 days

02/01/02

31/12/02

T.B.D.

Deliverables:

Not applicable.

Resources required:

95 NCO man days.

Success Measures:

Complete transfer of NATO CALS activities and products to the new CPG by December 2002.

Status Report: